§ 13-12-360

Permits required

No electrical equipment shall be installed or altered except upon a permit first issued by the department of buildings authorizing the installation, alteration, or repair of electrical equipment.

a.

If an electrical installation is commenced prior to the issuance of a permit for such work, the permit fee, for such work shall be twice the amount of the regular permit fee set forth in Section 13-32-310(b).

b.

Where a registered electrical contractor is found doing electrical work without a permit on three separate occasions in one calendar year, a hearing shall be held by the building commissioner at which time the permit privileges of said electrical contractor may be suspended for a period of time not to exceed one year.

c.

When contracts to install electrical work have been obtained by persons who are not registered as electrical contractors, as provided for in this article and the contract is assigned or sublet to a registered electrical contractor on a subcontract basis, the name of such registered electrical contractor shall immediately be disclosed by the registered electrical contractor to the other party to the contract in writing.

(Added Coun. J. 11-3-99, p. 13842, § 2; Amend Coun. J. 3-5-03, p. 104990, § 17; Amend Coun. J. 11-13-07, p. 14999, Art. II, § 1; Amend Coun. J. 12-12-07, p. 17167, § 13)